VERSION SCAFFMAX 2021


Description

After the scaffolding for all walls has been planned, the automatic scaffolding can take place. With the function scaffmax generation | Scaffold in the scaffmax program bar, all walls are automatically scaffolded for which wall data have been planned.

Prerquisites

Steps

  1. Click Scaffold  in the scaffmax command bar.
  2. The scaffolding is automatically built based on the settings selected in the WallData dialog.
  3. If scaffolding has already been defined on adjacent wall surfaces, scaffolding connections are created automatically.

Result

All walls for which wall data were defined were automatically scaffolded.